Status
SOUTH SIDE VIEW : K & L Block South side external wall Primer works in progress - 28th February 2021
TOWARDS NORTH SIDE VIEW : K Block Board games room internal plastering works in progress. External primer works in progress - 28th February 2021
PODIUM SIDE VIEW : K Block External wall Primer works in progress - 28th February 2021
PODIUM SIDE VIEW : N Block External wall Primer works in progress - 28th February 2021
TOWARDS WEST SIDE VIEW : L Block West Side View; Waterproofing works in progress at podium level - 28th February 2021
TOWARDS NORTH SIDE VIEW : M Block North Side View; External plastering works completed - 28th February 2021
TOWARDS PODIUM SIDE VIEW : M Block External plastering works completed - 28th February 2021
TOWARDS WEST SIDE VIEW : N Block External plastering works completed - 28th February 2021
TOWARDS NORTH SIDE VIEW : N Block 52 & 53 Series flat external plastering works completed - 28th February 2021
WEST SIDE VIEW : P Block tiling works in progress - 28th February 2021
WEST SIDE VIEW : P Block tiling works in progress - 28th February 2021
WEST SIDE VIEW : P Block West side wall external plastering works in progress - 28th February 2021
TOWARDS EAST SIDE VIEW : P Block 57 Series flat final Coat Final works completed - 28th February 2021
PODIUM SIDE VIEW : J Block Internal plastering works in progress - 28th February 2021
PODIUM SIDE VIEW : H Block Third Floor shuttering works in progress - 28th February 2021
NORTH SIDE VIEW : A Block Blockwork completed - 28th February 2021
PODIUM VIEW : Block A External plastering View - 28th February 2021
NORTH SIDE VIEW : A Block 2 Series flat external plastering works in progress - 28th February 2021
NORTH SIDE VIEW : Block S & R Northside View - 28th February 2021
PODIUM SIDE VIEW : Block S Indoor games room shuttering works in progress at 2nd floor level - 28th February 2021
SOUTH SIDE VIEW : Block D Terrace Floor slab completed - 28th February 2021
EAST SIDE VIEW : B Block Terrace Floor slab completed. C Block Gym area shuttering works in progress - 28th February 2021
NORTHSIDE COMPOUND WALL : 28th February 2021
BASEMENT CEILING VIEW : Cable tray In progress at Block J, K, L, M, N & P Blocks - 28th February 2021
BASEMENT CEILING VIEW : Ceiling Putty & Primer Works In progress at Block E, F, G, H, J, K, L, M, N & P Blocks - 28th February 2021
BASEMENT LEVEL : Basement Flooring works in progress at Block K, L, M, N & P - 28th February 2021
Speak to us
Thank you for contacting us we will get back to you!