Parkside East status images

Block K, L, M, N, P, Q, R, S, A, E, F and D: Basement Flooring VDF works in progress – 53% completed - Aug 2021

Parkside East status images

Block K, L, M, N, P, Q, R, S, A, E, F and D: Basement Flooring VDF works in progress – 53% completed - Aug 2021

Parkside East status images

Basement Level: Basement Putty & Primer works - In progress at Block J, K, L, M, N, P, Q, R, S, E, F, G, H and A Blocks - Aug 2021

Parkside East status images

Basement Level: Basement Putty & Primer works - In progress at Block J, K, L, M, N, P, Q, R, S, E, F, G, H and A Blocks - Aug 2021

Parkside East status images

Lift Erecting Works in progress: At Block Q, R, F, G, H and A - Aug 2021

Parkside East status images

Lift Erecting Works in progress: At Block Q, R, F, G, H and A - Aug 2021

Parkside East status images

West Side Compound Wall - Aug 2021

Parkside East status images

North Side Compound Wall - Aug 2021

Parkside East status images

Block H & G: Toilet dado Works in progress - Aug 2021

Parkside East status images

Lift Cladding: Block G, J - Lift dado Works in progress - Aug 2021

Parkside East status images

East Side View: Block C - External plastering works completed - Aug 2021

Parkside East status images

Podium Side View: Block D - External plastering completed, painting works in progress - Aug 2021

Parkside East status images

South Side View: Block C & D - South side external plastering works in progress - Aug 2021

Parkside East status images

East Side View: Block B - Northside external plastering works completed - Aug 2021

Parkside East status images

East Side View: Block B - Northside external plastering works completed - Aug 2021

Parkside East status images

North Side View: Block S - Multi-purpose hall and 3rd floor level blockwork in progress - Aug 2021

Parkside East status images

South Side View: Block G to K - Aug 2021

Parkside East status images

Block G & F: Block G - Podium side External plastering works completed, painting works. Block F - Podium side external plastering works in progress - Aug 2021

Parkside East status images

Podium Side: Block Q & R - External plastering works in progress - Aug 2021

Parkside East status images

North Side: Block Q - External plastering works in progress - Aug 2021

Parkside East status images

Podium Side: Block H - External plastering works completed, painting works in progress - Aug 2021

Parkside East status images

North Side: Block N to P - External painting works and window fixing works in progress - Aug 2021

Parkside East status images

North Side: Block N to B – Driveway road works in progress - Aug 2021

Parkside East status images

Podium Side Block N: External texture and painting works in progress towards podium side - Aug 2021

Parkside East status images

Podium Side Block L & M: External texture and painting works in progress towards podium side - Aug 2021

Parkside East status images

Podium Side Block M: External texture and painting works in progress - Aug 2021

Parkside East status images

Block K: Podium Side View - Aug 2021

Parkside East status images

Podium Side View: Block J - External texture painting works in progress - Aug 2021

Parkside East status images

West Side Block L & M: External painting works in progress - Aug 2021

Parkside East status images

Block N, P and J: Staircase Flooring Works in progress at basement and above floor levels - Aug 2021

Parkside East status images

Block K, L & M: Staircase Flooring Works in progress - Aug 2021

Parkside East status images

Block K, L and M : Shaft covering works in progress - Aug 2021

Parkside East status images

Block J, K, L, M, N, P, J, G, E: Balcony tiling works in progress - Aug 2021

Parkside East status images

Block G, H, J, K, L, M, N, P, A and E: Flat painting works in progress - Aug 2021

Parkside East status images

Block G, H, J, K, L, M, N, P, A and E: Flat painting works in progress - Aug 2021

Parkside East status images

Block G, H, J, K, L, M, N, P, A and E: Flat painting works in progress - Aug 2021

Parkside East status images

Block G, H, J, K, L, M, N, P, A and E: Flat painting works in progress - Aug 2021

Parkside East status images

Block G, H, J, K, L, M, N, P, A and E: Flat painting works in progress - Aug 2021

Parkside East status images

Block G, H, J, K, L, M, N, P, A and E: Flat painting works in progress - Aug 2021

Parkside East status images

Block G, H, J, K, L, M, N, P, A and E: Flat painting works in progress - Aug 2021

Parkside East status images

Block K, L, M and N: Window & door fixing works in progress - Aug 2021

Parkside East status images

Block K, L, M and N: Window & door fixing works in progress - Aug 2021

Parkside East status images

Block C: East side view - Entry pergola works in progress - Aug 2021

Parkside East status images

Block C: East side view - External plastering works completed, external primer works in progress at east side - Aug 2021

Parkside East status images

Block C: East side view - External plastering works completed, external primer works in progress at east side - Aug 2021

Parkside East status images

Block C East side view: External plastering works completed, external primer works in progress - Aug 2021

Parkside East status images

Block C: Southside view - C 12 series Internal plastering works completed, external plastering works in progress at south side - Aug 2021

Parkside East status images

Block C: All floor connecting corridor view - Podium side plastering works in progress - Aug 2021

Parkside East status images

East Side View: Block C - External plastering works completed. - Aug 2021

Parkside East status images

Blocks K, L, M and N: On commencement of fixing of doors and windows - Sep 2021

Parkside East status images

Blocks K, L, M and N: On commencement of fixing of doors and windows - Sep 2021

Parkside East status images

Blocks K, L, M and N: On commencement of fixing of doors and windows - Sep 2021

Parkside East status images

Blocks K, L, M and N: On commencement of fixing of doors and windows - Sep 2021

Parkside East status images

Blocks K, L, M and N: On commencement of fixing of doors and windows - Sep 2021

Parkside East status images

Blocks K, L, M and N: On commencement of fixing of doors and windows - Sep 2021

Parkside East status images

Blocks K, L, M and N: On commencement of fixing of doors and windows - Sep 2021

Parkside East status images

Blocks K, L, M and N: On commencement of fixing of doors and windows - Sep 2021

Parkside East status images

Block J: On commencement of Painting works - Aug 2021

Parkside East status images

Block J: On commencement of Painting works - Aug 2021

Parkside East status images

Block J: On commencement of Painting works - Aug 2021

Parkside East status images

Block A: On Commencement of Flooring works - Aug 2021

Parkside East status images

Block G: On Commencement of Flooring works - Aug 2021

Parkside East status images

Block G: On Commencement of Flooring works - Aug 2021

Parkside East status images

Block G: On Commencement of Flooring works - Aug 2021

Parkside East status images

Block G: On Commencement of Flooring works - Aug 2021

Parkside East status images

Block F: On Commencement of Installation of Lift - Aug 2021

Parkside East status images

Block G: On Commencement of Installation of Lift - Aug 2021