Block K, L M & N - External Plastering work in progress - July 2020

parkside-north-by-brigade-status

BLOCK K, L, M, N : Structure, Blockwork, MS Works Completed, 4TH floor plastering works are in progress - July 2020

parkside-north-by-brigade-status

BLOCK O, P, J & I : Terrace slab completed, 3rd and 4th floor Block work in progress - July 2020

parkside-north-by-brigade-status

BLOCK Q, R, G & H: Terrace slab completed, Wing G H 2nd floor, R Wing 1st floor Block work and in progress - July 2020

parkside-north-by-brigade-status

BLOCK S, T, F & E : Ground floor slab works are in progress - July 2020

parkside-north-by-brigade-status

BLOCK U, V, D & C : GF Slab completed, Wing V 1st Floor Slab work in progress - July 2020

parkside-north-by-brigade-status

BLOCK A, B, W & X : Wing A 2nd floor slab Completed, wing B X 2nd floor slab works in progress - July 2020

parkside-north-by-brigade-status

Block O : Block works are in progress - July 2020

parkside-north-by-brigade-status

Block K : Plastering works are in progress - July 2020

parkside-north-by-brigade-status

BLOCK K, L M, N : Tiles work in progress - July 2020

parkside-north-by-brigade-status

Block K, L, M N : Lift erection work in progress - July 2020

parkside-north-by-brigade-status

Basement putty works are in progress - July 2020

parkside-north-by-brigade-status

South side retaining wall work in progress - July 2020

parkside-north-by-brigade-status

Lower Basement Drain work under progress - July 2020

parkside-north-by-brigade-status

North side MS Fencing work in progress - July 2020